Construction
Update 11/21/2014
Update 10/2/2014
Update 10/2/2014
Update 9/3/2014
Update 4/1/2014
Update 2/5/2014: Dexter Station is on to the next level and on track for Completion Q1 2015!
Update 1/4/2014: Dexter Station rings in the new year and is now at street-level on the Aurora Avenue side.
Update 12/03/2013: Happy Holidays! The fifth floor is under construction and our crane gets decorated for the holidays.
Update 10/30/2013: A little rain doesn't stop Dexter Station's progress! The third floor is under construction.
Update 10/4/2013: First floor is under construction.
Update 8/30/2013: Foundation and interior columns are set.
Update 7/1/2013: Grading complete; construction continues ahead of schedule.
Update 6/2/2013: Wall goes up on Dexter Avenue side.
Update 4/1/2013: Aerial
photos of the construction site
Update 3/27/2013: Pilings along Aurora Avenue are all in. North and South drilling continues, as well as grading.