CONSTRUCTION SCHEDULE
Download full construction schedule
ID |
TASK NAME | DURATION |
START |
FINISH |
1 |
Entitlements and Permits | 118 days |
Wed 7/23/08 |
Mon 1/5/09 |
2 |
MUP Ready to Issue | 0 days |
Wed 7/23/08 |
Wed 7/23/08 |
3 |
Shoring and Garage Permit Ready to Issue | 0 days |
Wed 8/27/08 |
Wed 8/27/08 |
4 |
Building Permit Ready to Issue | 0 days |
Mon 1/5/09 |
Mon 1/5/09 |
5 |
Permits Complete | 0 days |
Mon 1/5/09 |
Mon 1/5/09 |
6 |
||||
7 |
Design and Docs | 0 days |
Tue 9/30/08 |
Tue 9/30/08 |
8 |
Construction Documents Complete | 0 days |
Tue 9/30/08 |
Tue 9/30/08 |
9 |
||||
10 |
Preleasing Phase | 131 days |
Tue 9/30/08 |
Tue 3/31/09 |
11 |
Pending | 131 days |
Tue 9/30/08 |
Tue 3/31/09 |
12 |
||||
13 |
Building Construction | 457 days |
Wed 4/1/09 |
Thu 12/30/10 |
14 |
Site Mobilization | 12 days |
Wed 4/1/09 |
Thu 4/16/09 |
15 |
Shoring & Excavation - Can start 8/27/08 | 68 days |
Fri 4/17/09 |
Tue 7/21/09 |
16 |
Garage Construction | 65 days |
Wed 7/22/09 |
Tue 10/20/09 |
17 |
Building Construction | 312 days |
Wed 10/21/09 |
Thu 12/30/10 |