CONSTRUCTION SCHEDULE

Download full construction schedule

ID
TASK NAME
DURATION
START
FINISH
1
Entitlements and Permits
118 days
Wed 7/23/08
Mon 1/5/09
2
    MUP Ready to Issue
0 days
Wed 7/23/08
Wed 7/23/08
3
    Shoring and Garage Permit Ready to Issue
0 days
Wed 8/27/08
Wed 8/27/08
4
    Building Permit Ready to Issue
0 days
Mon 1/5/09
Mon 1/5/09
5
    Permits Complete
0 days
Mon 1/5/09
Mon 1/5/09
6
       
7
Design and Docs
0 days
Tue 9/30/08
Tue 9/30/08
8
    Construction Documents Complete
0 days
Tue 9/30/08
Tue 9/30/08
9
       
10
Preleasing Phase
131 days
Tue 9/30/08
Tue 3/31/09
11
    Pending
131 days
Tue 9/30/08
Tue 3/31/09
12
       
13
Building Construction
457 days
Wed 4/1/09
Thu 12/30/10
14
    Site Mobilization
12 days
Wed 4/1/09
Thu 4/16/09
15
    Shoring & Excavation - Can start 8/27/08
68 days
Fri 4/17/09
Tue 7/21/09
16
    Garage Construction
65 days
Wed 7/22/09
Tue 10/20/09
17
    Building Construction
312 days
Wed 10/21/09
Thu 12/30/10